WORK ON HOHOE TOWN ROADS PROGRESSES (PAGE 35)

WORK on the three-kilometre Hohoe town roads in the Volta Region is progressing steadily.
The Managing Director of Survivors Construction Limited, Mr Castro Dela Ahorsu, executor of the project, told the Daily Graphic that 65 per cent of the job had been completed.
He was reacting to the concerns raised by the people of Hohoe about the slow pace of work and the dust which had engulfed the town.
Mr Ahorsu stated that the contract involved the construction of three kilometres of the main road in the town and said he had already finished constructing the drains and slabs.
He said within the next three weeks, he would start with prima sealing and expressed the hope that the entire project would be completed by the end of July, this year.
Touching on the type of materials he was using for the project, he said the Ghana Highway Authority (GHA) had given approval for these.
The Technical Assistant in charge of Materials of the GHA at Ho, Mr Wisdom Amuzu, confirmed the approval of the materials being used for the project.